07/06/2011 continuation of scaffolding, putting on the roof frames
to day we were down the site, finishing of our scaffolding, me and a couple of the boys were working at the back setting up the scaffold there, grabbing sole plates, 2 6m poles and the rest were 2.4m poles... we used it to set up our scaffolding and then used swivels, connectors, fixed clamps to help hold it and used a wrench to tighten the screw, after we had set up our scaffold at th back. we then grabed planks and put it on top of the putlogs. then we had to make another platform, so we can get up on the roof etc,.. after that we had to make steps so its easier for us to get on the platform. then mason Jonathon marked out where the trusses will go, they marked it on top of the top plate.. after that we started bring our roof frames on top of the house just laying them on top of the top plates waiting for tomorrow to fix them in.